A project team that uses what three strategies would achieve MR Credit Interiors

[复制链接]

1759

主题

1

好友

5688

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2016-9-23 11:52:42 |只看该作者 |倒序浏览
试卷: LEED v4 ID+C模拟题A卷英文[查看]
A project team that uses what three strategies would achieve MR Credit Interiors Life-Cycle Impact Reduction, Design for Flexibility?(Choose 3)
A: Ensure that at least 50% of nonstructural materials, by cost, are reusable or recyclable
B: Obtaining commitment from the entire project team to ensure flexible strategies are not value-engineered out
C: Include in at least one major component or systems purchase contract a clause specifying sub-contractor, vendor, or on site t
D: Reuse, salvage, or refurbish furniture and furnishings for at least 30% of the total furniture and furnishings cost.
E: Design at least 50% of interior nonstructural walls, ceilings, and floors to be movable or demountable

参考答案: ACE

本题解释:
Notes:Use at least three of the following strategies.
Install accessible systems (floor or ceiling) for at least 50% of the project floor area to allow for flexible use of space and access to systems (under floor distribution systems) not entangled with other building systems.
Design at least 50% of interior nonstructural walls, ceilings, and floors to be movable or demountable.
Ensure that at least 50%, by cost, of nonstructural materials have integral labels.
Include in at least one major component or systems purchase contract a clause specifying sub-contractor, vendor, or on site take back system.
Ensure that at least 50% of nonstructural materials, by cost, are reusable or recyclable.
Implement flexible power distribution (i.e., plug-and-play) systems for at least 50% of the project floor area so that lighting, data, voice, and other systems can be easily reconfigured and repurposed.
Implement a flexible lighting control system with plug and play components such as wall controls, sensors, and dimming ballasts for a minimum of 50% of the lighting load.
B:This is part of developing goals but is not required for the credit. D:This is for Option 2.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-6-26 18:06 , Processed in 0.079330 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部