试卷: LEED v4 ID+C模拟题A卷英文[查看] Which action would a third-party commissioning agent most likely take in the pre-design phase of a project? A: Research the assumptions regarding usage of the facility B: Write the Basis of Design (BOD) C: Collect specific manufacturer makes and models for drawings and specs D: Verify that the architect\'s and engineer\'s designs meet the owner\'s project requirements 参考答案: D
本题解释: Notes:A: This is part of the BOD. B:The BOD is \'the information necessary to accomplish the owner\'s project requirements, including system descriptions, indoor environmental quality criteria, design assumptions, and references to applicable codes, standards, regulations, and guidelines.\' - USGBC
The CxA does not write this document. C:This is part of the BOD. D: The CxA needs to verify the OPR, BOD, and project design. |
|