试卷: LEED v4 ID+C模拟题D卷英文[查看] The number of occupants, their function, and the occupancy schedules for the building would be noted in which document? A: The Basis of Design (BOD) B: The Owner\'s Project Requirements (OPR) C: The Cx Report D: The Current Facilities Requirements (CFR) 参考答案: B
本题解释: 选择B,本题解释 See the Further Explanation in the prerequisite for the different document types and what each includes (too extensive to include here). Test-takers should be familiar with the content that goes into each of the following:
OPR
BOD
Cx Plan
Cx Report
CFR and Operations and Maintenance plan
Systems Manual (Enhanced Cx)
Ongoing Cx Plan (Enhanced Cx) |
|