试卷: LEED v4 ID+C模拟题D卷英文[查看] The owner an office project wants to use 50% green power, but the direct purchase of Green-e certified power is not available through the local utilities. An energy model was not done for EA Credit, Optimize Energy Performance. What information is NOT required when determining the quantity of RECs to purchase? A: Median electrical intensity (kWh/sf-yr) B: Total building area (sq. ft.) C: Emissions criteria for the non-renewable portion of the electricity D: Building type 参考答案: C
本题解释: 选择C,本题解释The question asks what information will not be required. Emissions criteria would not be used.
The CBECS database uses the building type and total building area to determine the default electricity consumption.
The median electrical intensity will be used to determine the required green power quantity. |
|