试卷: LEED AP ND模拟题A[查看] Which site would be classified as an infill site?
A: A site that with water front borders for 50% of its borders B: Site with a preproject connectivity of 140 intersections per square mile within 1/2 mile distance from the project C: A site that, preproject, was 100% previously developed land D: A site surrounded by four streets 参考答案: B
本题解释: A:Portions of the project that border waterfronts are excluded.
B:If a site meets any of these four conditions it is considered an infill site:
At least 75% of its boundary borders parcels that individually are at least 50% previously developed, and that in aggregate are at least 75% previously developed
The site, in combination with bordering parcels, forms an aggregate parcel whose boundary is 75% bounded by parcels that individually are at least 50% previously developed, and that in aggregate are at least 75% previously developed
At least 75% of the land area, exclusive of rights-of-way, within a 1/2 mile distance from the project boundary is previously developed
The lands within a 1/2 -mile distance from the project boundary have a preproject connectivity of at least 140 intersections per square mile
C:This would be considered previously developed (75% minimum).
D:Streets are not considered previously developed land.
|
|