试卷: LEED v4 GA模拟题A卷中文[查看] 下列哪项不是减少施工废弃物的措施?Which of the following is NOT a strategy to reduce construction waste? A: 最大化建筑基底 Maximize the building footprint B: 废物再利用 Use salvaged materials C: 循环利用材料 Recycle materials D: 出售未使用的材料 Sell unused materials 参考答案: A
本题解释: 正确答案:A
系统解析: 暂无解析
A:Increasing the size of the building footprint would likely increase the amount of construction waste.
Notes:
Note the question asks what is not a strategy.
To reduce construction waste, divert any unused materials from the waste stream-namely, landfills and incinerators.