试卷: LEED v4 BD+C中文模拟题(A)[查看] 在尝试获得能源与大气(EA)先决条件:最小能效表现之前,所有项目第一步必须做什么?Which first step must all projects take before attempting EA Prerequisite Minimum Energy Performance? A: 审查ASHRAE 90.1强条内容 Review the mandatory components of ASHRAE 90.1 B: 创建基准能耗模型 Create a baseline energy model C: 确定项目气候分区 Determine the project’s climate zone D: 确定项目是否要做围护结构调试 Determine if the project will be doing envelope commissioning 参考答案: C
本题解释: 正确答案:C
解析:C:气候分区确定后才能知道需要遵循ASHRAE 90.1中的哪些强条要求,不管项目是否要进行能耗模拟或采用规定性达标路径。The climate zone determines which mandatory requirements from ASHRAE need to be followed, regardless of if an energy model or prescriptive compliance is pursued.
A:这是第二步。 This is Step 2 of the process.
B:创建基准能耗模型一般发生在整个建筑能耗模拟的时候。 This occurs later for a whole-building energy simulation.
D:这不属于先决条件过程的步骤。This is not part of the prerequisite process. |
|