A project has a 150-kW PV array that will produce 210,458 kWh of electricity per

[复制链接]

1759

主题

1

好友

5712

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2016-9-30 08:57:16 |只看该作者 |倒序浏览
试卷: LEED v4 ID+C模拟题C卷英文[查看]
A project has a 150-kW PV array that will produce 210,458 kWh of electricity per year after transmission and conversion losses. The virtual rate for the electricity generated is $0.092/kWh. The total tenant-level annual energy cost as determined from CBECS is $60,129. What percentage of renewable energy will the system produce?
A: 29%
B: 32%
C: 55%
D: 28%

参考答案: B

本题解释:
Notes:
210,458 kWh X $0.092 / kWh = $19,362
$19,362 / $60,129 = 32%
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-9-12 20:08 , Processed in 0.079614 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部