试卷: LEED v4 ID+C模拟题C卷英文[查看] If a project team is pursuing the prescriptive path of WE Prerequisite Indoor Water Use Reduction, which action should occur in order to document compliance? A: Calculate any additional savings from using non-potable water B: Complete the calculations for the design case (installed) flush and flow fixtures C: Ensure fixtures meet the prescriptive flush/flow rates and collect manufacturer cutsheets for all fixtures and appliances D: Verify project occupancy, gender ratios, and annual days of operation 参考答案: C
本题解释: Notes:A:This is necessary for usage-based calculation for the credit.B:This is necessary for usage-based calculation.C:For the prerequisite, this is what must be done.D:
This is necessary for usage-based calculation. |
|