试卷: LEED v4 ID+C模拟题D卷英文[查看] A CxA has finished preparing their Cx report for the building owner, and the project team is compiling the current facility requirements (CFR) and operations and maintenance (O&M) plan. Which information should the CFR and O&M plan include to operate a building efficiently by the facility manager? A: Subcontractors contact information, issues log, team member roles B: System deficiencies, air quality measurements, occupant surveys C: Installation verification checklist, design review log, functional performance tests D: Set points for all HVAC equipment, sequence of operations for the building, lighting levels 参考答案: D
本题解释: 选择D,本题解释There are 10 items the O&M plan must include (see the reference guide). |
|