试卷: LEED v4 ID+C模拟题D卷英文[查看] A project team is conducting a one-week flush of an office during the summer for EQ Credit IAQ Assessment. During the flush-out, the painting contractors come back to complete paint touch-ups of the interior. Which statement is true about this scenario? A: As long as the paint contains low-VOCs, no additional steps are necessary. B: No additional time or testing is required for the flush-out. C: Air-quality testing now additionally needs to be performed for those rooms receiving paint touch-ups. D: The flush-out has to be re-started from the beginning. 参考答案: D
本题解释: 选择D,本题解释No construction work can occur during either the flush-out or the air-quality testing.
If any punch-list items that generate VOCs or other contaminants occur during either, the flush-out/testing must start again. |
|