Why should building commissioning be performed?

[复制链接]

1759

主题

1

好友

5684

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-9-7 21:49:40 |只看该作者 |正序浏览
试卷: LEED GA模拟题C[查看]
Why should building commissioning be performed?
A: It is required by local code prior to earning a Certificate of Occupancy
B: An innovation credit can be earned
C: Sustainable purchasing programs require it
D: Operating costs can be lowered and energy use can be reduced

参考答案: D

本题解释:
Notes:

Reference: LEED 2009 for New Construction and Major Renovations Rating System
A: This is not correct.
B:Fundamental commissioning is a prerequisite and it cannot earn an ID credit.
C:Sustainable purchasing has nothing to do with commissioning.
D:Commissioning is the systematic process of assuring that a building and its systems performs in accordance with the design intent and the owner\'s requirements. This is part of building construction.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-5-7 06:27 , Processed in 0.080476 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部