What is a stakeholder meeting?

[复制链接]

1759

主题

1

好友

5684

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-9-7 21:49:40 |只看该作者 |正序浏览
试卷: LEED GA模拟题E[查看]
What is a stakeholder meeting?

A: A meeting where research is conducted about materials
B: An intense workshop to solve a problem or plan the design of something that includes the project team and stakeholders
C: A meeting where engineers work together to discover new synergies
D: A meeting with everyone that has a vested interest in the outcome of a project

参考答案: D

本题解释:
Notes:

Reference: GBES LEED Green Associate Study Guide
A:This is an example of a small task group meeting.
B:This is a charrette. Also included in the charrette are any external experts that might be needed for consultation. An example would be a sales engineer for a specific product.
C:This is an example of a team meeting.
D:This is an example of a stakeholder meeting. Stakeholders involve everyone that may be impacted by the project. An example is if a new residential project is being planned, the existing neighbors would be invited to the meeting to voice their input and concerns. Also included would be city planners, engineers, building owners, general contractors, etc.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享1 收藏收藏1
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-5-7 06:34 , Processed in 0.077071 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部