What must a project do to earn LEED certification after selecting a rating system?
A: Satisfy all prerequisites for the selected rating system and earn a minimum number of points
B: Earn a minimum number of points only
C: Satisfy relevant prerequisites for the selected rating system and earn a minimum number of points
D: Pay the relevant fees and have a Green Rater approve the project

参考答案: A

本题解释:
After selecting a rating system a project must satisfy all prerequisites and earn a minimum number of points to be certified.
Prerequisites must also be met.
\'Satisfy relevant prerequisites\' is not correct because project teams can\'t choose what prerequisites to meet for a given rating system. All prerequisites for the rating system the project will certify under must be followed.

At least 40 points must be earned for a building to be LEED Certified at the base level (Certified).

Certified 40-49 points
Silver 50-59 points
Gold 60-79 points
Platinum 80+ points
Green Raters are only relevant to the LEED for Homes rating system.
Reference: GBCI LEED Certification Policy Manual
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-5-7 06:28 , Processed in 0.074386 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部