试卷: LEED AP BD+C模拟题B[查看] For Enhanced Commissioning, when must the follow-up by the CxA be performed? A: 10 months after substantial completion B: 10 months after occupancy C: 10 months after LEED certification is awarded D: 10 months after a certificate of occupancy is issued 参考答案: A
本题解释: Notes:
Reference: Energy and Atmosphere Credit, Enhanced Commissioning, Requirements
The CxA must be involved in reviewing the operation of the building with operations and
maintenance (O&M) staff and occupants within 10 months after substantial completion. A plan for
resolving outstanding commissioning-related issues must be included. |
|