To qualify for the Community Connectivity credit, a project must be on a previou

[复制链接]

1759

主题

1

好友

5692

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-10-12 12:51:08 |只看该作者 |正序浏览
试卷: LEED AP BD+C模拟题E[查看]
To qualify for the Community Connectivity credit, a project must be on a previously developed site. Which of the following must also be true? (choose 2)
A: The project must be within 1/2 mile of a residential area
B: The project must be within 1/2 mile of two bus stops
C: The project shall be within 1/2 mile of at least 10 Basic Services
D: The project must be in a community with a density of 60,000 sq. ft. per acre net
E: The project must have a carpool drop off area

参考答案: AC

本题解释:
Notes:
See “Requirements” section of SS 2
Answer (d) is incorrect because it is part of Option 1- Development Density of SSc2.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-7-7 05:42 , Processed in 0.075374 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部