试卷: LEED AP ND模拟题C[查看] A project is located in a jurisdiction that provides recycling services and hazardous waste collection services. The project will include composting available to all occupants and will recycle/salvage 60% of nonhazardous construction and demolition debris. What else must the project include to qualify for GIB Credit Solid Waste Management Infrastructure?
A: Publicize the availability and benefits of the available services B: Including recycling containers at least every 800 feet on every mixed-use or nonresidential block C: Recycle/salvage and additional 15% of nonhazardous construction and demolition debris D: Include recycling containers on every nonresidential block 参考答案: A
本题解释: A:The requirements state the availability and benefits of services must be publicized.
C:60% meets the 50% minimum threshold. No addition is necessary.
Notes:
Reference: GIB C16, Requirements |
|