A project has residential density of 10 dwelling units / acre. The nonresidentia

[复制链接]

203

主题

0

好友

512

积分

超级版主

Rank: 8Rank: 8

跳转到指定楼层
楼主
发表于 2013-8-6 05:49:38 |只看该作者 |正序浏览
试卷: LEED AP ND模拟题D[查看]
A project has residential density of 10 dwelling units / acre. The nonresidential density is 0.50 FAR. What minimum percentage of the undeveloped area must remain undisturbed to earn GIB Credit Minimized Site Disturbance in Design and Construction?


A: 20%
B: 5%
C: 15%
D: 10%

参考答案: A

本题解释:
What you need to remember for this credit is the thresholds are 10%, 15%, and 20%. The minimum area to leave undisturbed is the greater percentage of the nonresidential density FAR or residential density / acre based on the values in the table.

In this example the 10 DU / acre require 20% minimum undisturbed area. The 0.5 FAR only requires 15%.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-7-8 00:08 , Processed in 0.077859 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部