试卷: LEED v4 GA模拟题C卷[查看] A developer is considering pursuing LEED for an eight-story, multi-family residential project. How would the baseline building performance be determined? A: By calculations made using ASHRAE 90.1 B: By the project obtaining a HERS index C: By obtaining an ENERGY STAR for Homes rating D: By using the EPA’s ENERGY STAR Portfolio Manager 参考答案: A
本题解释: 正确答案:A
系统解析: A:In LEED v4, BD+C projects use ASHRAE 90.1-2010 to determine the baseline building performance.
B:HERS index is for LEED for Homes projects. This question indicates that the project is an eight-story residential building, so LEED BD+C: Multifamily Midrise would be used.
C:LEED for Homes minimum energy performance requires meeting the requirements of ENERGY STAR for Homes.
D:EPA’s ENERGY STAR Portfolio Manager can be used to compare buildings of similar size and function (office to office, for example).
Notes:
The baseline building performance is ’the annual energy cost for a building design, used as a baseline for comparison with above-standard design.’ - USGBC
|
|