试卷: LEED v4 GA模拟题B卷中文[查看] 在项目最终递交进行认证之前,下列哪项是应该进行的最后步骤之一?Which of the following indicates one of the final steps that should occur prior to submitting the project’s final documentation for certification? A: 应在平面图上划定LEED项目边界 The LEED project boundary should be mapped. B: 应检查面积确保所有得分项都保持一致 The site area should be checked to make sure it is consistent across credits. C: 应挑选合适的LEED适用体系 The appropriate LEED adaptation should be selected. D: 优先考虑符合项目所处环境/背景以及项目团队、业主或组织的价值观相一致的认证策略 The strategies for certification that align with the project’s context and the value 参考答案: B
本题解释: 正确答案:B
系统解析:B: 在递交之前,项目团队应进行质量把关审查(Quality Assurance Review),包括各个得分项/先决条件递交文件是否完整,各个得分项采用的数据是否一致,如场地面积、建筑面积,所有得分项应保持一致。
B:A quality assurance review should occur prior to submitting documentation. The credit submissions should be proofread, checked for completeness, and numeric values (such as the site area) should be checked for consistency.
A:This is part of the LEED project scope and occurs long before submitting the final documentation.
C:This occurs earlier on in the process, not right before project certification.
D:This is part of establishing project goals. This occurs before any credit documentation is even started.
Notes:
This question tests knowledge on the LEED work plan or the recommended steps to certification.
|
|