试卷: LEED v4 GA模拟题B卷[查看] What is one of the primary tasks for an integrated project team during the Discovery phase?
A: Understanding system interactions B: Register the project via LEED Online C: Secure project financing D: Make certain there is a local waste hauler that recycles waste 参考答案: A
本题解释: 正确答案:A
系统解析: Knowledge Domain: Integrative Strategies
Approaching certification using an integrative process gives the project team the greatest chance of success. The process includes three phases: Discovery, Design and construction (implementation), and Occupancy, operations, and performance feedback. Discovery is the most important phase of the integrative process as collective understanding of system interactions are reached during the discovery phase.
Integrative process > early analysis of the interrelationships among systems [ Reference Guide Introductory and Overview Sections (Credit Category Overviews > Getting Started > Taking an Integrative Approach to Design and Construction): http://www.usgbc.org/guide/bdc ]
|
|