试卷: LEED v4 BD+C中文模拟题(A)[查看] 哪个项目团队成员在早期设计阶段加入材料与资源(MR)先决条件:施工与拆除废弃物管理计划中会帮助后期能获得相关的得分项? Integrating which project team member into MR Prerequisite Construction and Demolition Waste Management Planning early in the design phase will assist later with earning the related credit? A: 入住者 Occupants B: 承包商 Contractor C: 业主 Owner D: 设施经理 Facility Manager 参考答案: B
本题解释: 正确答案:B
解析:B:承包商需要早点知道先决条件和得分项的要求,这样更加有利于后期成功的实现目标。
Integrating the contractor early in the design phase will lead to success in the prerequisite and more substantial success in achieving the related credit.
Contractors need to be aware of the requirements in the prerequisite early on. |
|