A site is being selected for a company’s new corporate headquarters.What site i

[复制链接]

1759

主题

1

好友

5712

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2015-4-13 09:15:01 |只看该作者 |正序浏览
试卷: LEED v4 BD+C英文模拟题(A)[查看]
A site is being selected for a company’s new corporate headquarters.What site is the best choice if the project wants to qualify for LT Credit Sensitive land Protection?
A: 10 acres (4 hectares) currently owned by a farmer
B: A previously developed site near similar projects
C: Land that is the habitat for a rare species of animal
D: Previously undeveloped land with a 1% chance of flooding in any given year
E: 10 acres (4 hectares) of undeveloped land that is a currently an unused nature preserve

参考答案: B

本题解释:
正确答案:B
解析:Notes: The question asks for the “best” choice of site. “The best strategy for selecting a building site is to choose a previously developed site”.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-9-14 06:12 , Processed in 0.076538 second(s), 27 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部