试卷: LEED v4 ID+C模拟题A卷英文[查看] A project team for a small retail store is meeting early in the design process to discuss energy efficiency. When would it be appropriate for the team to pursue the prescriptive path of EA Prerequisite Minimum Energy Performance? A: If the project is located in a building that has a base building energy model B: If the primary efficiency upgrades focus on lighting, equipment, and appliances C: If the project is taking credit for the efficiency of a central plant D: If the project includes on-site renewable energy and intends to use the energy produced for additional points 参考答案: B
本题解释: Notes: B:Simple projects or projects that are looking for a cost-effective option should choose the prescriptive path. |
|