A hospitality project will include a common laundry room, postal area, and heated swimming pool. An independent CxA has been hired to help the project achieve EA Credit Enhanced Commissioning. What additional activities will the CxA be required for enhanced systems commissioning?(Choose 2)
A: Develop an on-going commissioning plan
B: Develop a systems manual for the heated swimming pool
C: Review contractor submittals applicable to the heated swimming pool
D: Verify that requirements for training are completed
E: Implement the commissioning plan

参考答案: AC

本题解释:
Notes:There are several responsibilities only the CxA can complete for Enhanced Systems Commissioning. Some items can be completed by the CxA or other members of the project team. The question specifically asks for items that the CxA is required to perform. So the correct answers can only be performed by the CxA.
Training can be done by the CxA or other project team member, that is why it is not a correct answer - the CxA is not required to do it.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-9-13 00:50 , Processed in 0.075064 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部