试卷: LEED v4 ID+C模拟题A卷英文[查看] A project team has developed a reuse strategy for some interior elements and calculated the project could earn points under MR Credit Interiors Life-Cycle Impact Reduction? What should the project team do to avoid issues earning the credit later on? A: Submit separated documentation for each project space B: Incorporating the reused elements into the construction documents C: Implement a construction waste management plan D: Make sure the tenant lease is signed 参考答案: B
本题解释: Notes:B:For this credit it\'s important to specify reuse and strategies in the construction documents clearly. Once items get demolished or thrown away the project team can’t go back if there was an error by the contractors. |
|