试卷: LEED v4 ID+C模拟题C卷英文[查看] A LEED ID+C project will be constructed and operated on a permanent location on existing land, and will be a minimum of 250 SF (22 m2). What else must the project do to meet the minimum program requirements? A: The project team must perform an preliminary energy analysis before the completion of schematic design B: The project must have at least one LEED AP on staff C: The owner must hire a CxA that has experience on at least two other LEED projects D: The project boundary must include all contiguous land that is associated with the project and supports its typical operation 参考答案: D
本题解释: Notes:A:This is one of the requirements for IP Credit Integrative Process.B:This can earn an IN credit.C:This is part of the commissioning requirements.D:This is the 3rd MPR the project would need to meet. |
|