试卷: LEED v4 ID+C模拟题C卷英文[查看] After the owner documents their owner\'s project requirements (OPR), the project team will take that document to create the basis of design (BOD). What would be contained in the BOD? A: Operating mode tests, sustainability goals, occupant functions B: Systems and assemblies, governing codes and standards, performance criteria and assumptions C: Energy efficiency goals, number of occupants, building schedule D: Functional testing, training requirements, issue resolution process 参考答案: B
本题解释: Notes: See the Further Explanation in the prerequisite for the different document types and what each includes (too extensive to include here). Test-takers should be familiar with the content that goes into each of the following:
OPR
BOD
Cx Plan
Cx Report
CFR and Operations and Maintenance plan
Systems Manual (Enhanced Cx)
Ongoing Cx Plan (Enhanced Cx) |
|