试卷: LEED v4 ID+C模拟题C卷英文[查看] If a building includes a multiple-zone recirculating system and the project team wants to increase ventilation for IEQ Credit Enhanced IAQ Strategies, which action will likely need to occur? A: Adding demand-controlled ventilation to the design B: Increasing the required outdoor air intake for the system by more than 30% C: Performing a simulation to determine if concentrations for pollutants regulated by NAAQS at outdoor air intakes are below the D: Installing MERV 13 (F7) filters 参考答案: B
本题解释: Notes:B:This would likely need to occur for this option.C:This step is used for exterior contamination prevention. |
|