试卷: LEED v4 ID+C模拟题C卷英文[查看] Which system is required to be included in the OPR and BOD if it is part of the scope of work, but does not have to be commissioned for Fundamental Commissioning and Verification? A: Fire protection and fire alarm systems B: The building envelope C: Process equipment D: Life safety systems 参考答案: B
本题解释: Notes: Mechanical, electrical, plumbing, and renewable energy systems and assemblies must be commissioned for the prerequisite.
The OPR must include the building envelope if it is part of the scope of work, but it doesn\'t have to be commissioned.