试卷: LEED v4 ID+C模拟题D卷英文[查看] What housekeeping tasks must be completed to meet SMACNA requirements for EQ Credit IAQ Management Plan during construction?(Choose 2) A: Using wetting agents for dust B: Store all porous building materials outside of the construction area until they are needed C: Use vacuum cleaners with high-efficiency particulate filters D: Ventilate the construction area at least weekly with outside air 参考答案: AC
本题解释: 选择AC,本题解释A.Using wetting agents for dust is recommended for housekeepings. B.Porous building materials need to be stored and protected from moisture damage, but they do not have to be stored outside of the construction area. They should be kept where there are low humidity levels and protected from water. C.Use high efficiency particulate filters in vacuum cleaners. D.Ventilating the construction area helps with Pathway Interruption, not Housekeeping. |
|