试卷: LEED v4 ID+C模拟题D卷英文[查看] A 2-story mixed use project will have retail space on the first floor and hospitality space on the second floor. Since there more than two rating systems that might be applicable to a project, how should the project team decide which rating system to use?
A: Use both rating systems and achieve all rating system specific credits for both LEED ID+C: Retail and LEED ID+C: Hospitality B: Choose the rating system that will result in the lowest certification costs C: Check the local code official what rating system to use D: Check the local code official what rating system to use 参考答案: D
本题解释: 选择D,本题解释LEED has a 40/60 rule to help project teams decide on a rating system:
If a particular rating system is appropriate for 40% or less of a LEED project building or space, then that rating system should not be used.
If a particular rating system is appropriate for 60% or more of a LEED project building or space, then that rating system should be used.
Project teams with buildings and spaces that do not fall into the scenarios described in a) and b) must independently assess their situation and decide which rating system is most applicable.
|
|