试卷: LEED v4 OM模拟题A卷英文[查看] A project team will earn two points for WE Credit Cooling Tower Water Use by meeting the maximum number of cycles without additional treatment. Which action can the project team take to earn additional points?
项目团队将在WE得分项冷却塔用水中获得两分,因为项目无需额外处理即可满足最大循环次数要求。项目团队可以采取哪些措施来获得额外得分?
A: Increase the concentrations in the condenser water增加冷凝水浓度 B: Add filtration增加过滤 C: Decrease the number of cycles of concentration 减少浓度循环次数 D: Use 20% alternative water sources 使用20%的替代水源 参考答案: D
本题解释: 选择D,本题解释 A.The goal is to decrease the concentrations. C.The goal is to increase the cycles. D.If a project meets the minimum number of cycles to earn two points, an additional 1-2 points (depending on the rating system) can be earned by using at least 20% recycled non-potable water.
|
|