试卷: LEED v4 OM模拟题C卷英文[查看]   A project site already meets the 5% vegetation threshold for SS Credit Site Improvement Plan during the performance period. What does the site improvement plan need to include to meet the credit requirements?
 在绩效期内,项目场地已经达到了SS 得分项 场地改良计划 5%的场地面积有植被覆盖的要求。场地改良计划还需要包括什么来满足得分项要求?   A: The irrigation schedule for the area 该区域的灌溉时间表 B: How the existing vegetated area will be protected 现有的植被区域如何被保护 C: The maintenance plan for the existing vegetated area 既有植被场地的维护计划 D: A requirement to increase the vegetated area to 10% 要求将有植被区域扩大到场地面积的10%     参考答案: B 
  本题解释: 选择B,本题解释Document in the plan how the existing area will be protected. |   
 
  
 |