试卷: LEED v4 OM模拟题D卷英文[查看]   A third-party consultant has been hired to perform an ASHRAE Level 1 energy audit. What should the project team verify is included in the final report?
 某项目由第三发顾问来执行ASHRAE Level 1能源审计,在最终报告中需要包括什么内容   A: Plumbing schedule 洁具清单 B: Payback period and maintenance implications of no-cost and low-cost improvements 低成本及无成本改进措施的投资回报计算和相关影响 C: Summary of the intended operation of each system described in the systems narrative 系统总结 D: Current state of systems 目前系统状况     参考答案: B 
  本题解释: 选择B,本题解释A.This is part of the CFR.  B.A financial assessment of any no/low cost improvements must be included as well as:
 
 
 Comparison with similar building types
 Current energy indexes
 Energy use breakdown 
 C.This is part of the building operating plan.  D.This is part of the O+M plan. |   
 
  
 |