试卷: LEED AP BD+C模拟题D[查看] A project will use 10,000 gallons of graywater and 5,000 gallons of rainwater for building
sewage conveyance. Low flow urinals and water closets will also be used in the project.
What information would be included in the calculations of the baseline case for Water
Efficiency Credit, Innovative Wastewater Technologies? A: Fixture types B: 10,000 gallons of graywater C: Flow rate of the low-flow urinals D: 5,000 gallons of rainwater 参考答案: A
本题解释: Notes:
The baseline case for Water Efficiency Credit, Innovative Wastewater Technologies uses
the fixture flow rates from the Energy Policy Act of 1992. The baseline case does not
include any low-flow fixtures, or captured rainwater/graywater used.
Both the design and the baseline case include the fixture types, the daily uses by all FTEs,
and the annual volume. |
|