注册时间2012-6-6最后登录2025-9-5阅读权限200积分5712精华3帖子1765
 
   
 | 
| 试卷: LEED AP ID+C 模拟试卷A[查看] What is an important difference between the energy cost budget and the performance rating method for Energy and Atmosphere Credit, Optimize Energy Performance-HVAC, Requirements?
 A: The performance rating method allows projects to trade off energy performance between building systems
 B: The energy cost budget excludes exhaust fans
 C: The performance rating method excludes facade lighting
 D: The energy cost budget does not recognize energy-efficient design of air distribution systems
 
 参考答案: D
 
 本题解释:
 Reference: Energy and Atmosphere Credit, Optimize Energy Performance-HVAC, Calculations, Option 2
 
 The energy cost budget does not recognize energy-efficient design of air distribution systems and the performance rating method does.
 
 Both of the methods include exhaust fans, facade lighting, and all end-use load building components.
 | 
 |