试卷: LEED AP ND模拟题C[查看] A project will include new multiunit residential buildings 3 stories high. What must occur for the project to qualify for GIB Prerequisite Minimum Building Energy Efficiency?
A: 90% of the building floor area must demonstrate an average of 10% improvement over ASHRAE 90.1-2007 B: 90% of the buildings must demonstrate an average of 10% improvement over ASHRAE 90.1-2007 C: 90% of the building floor area must meet ENERGY STAR or equivalent criteria D: 90% of the buildings must meet ENERGY STAR or equivalent criteria 参考答案: D
本题解释: For new multiunit residential buildings three stories or fewer 90% of the buildings must meet ENERGY STAR or equivalent criteria.
|
|