For a mechanically ventilated space, what should a project team do to achieve IE

[复制链接]

203

主题

0

好友

512

积分

超级版主

Rank: 8Rank: 8

跳转到指定楼层
楼主
发表于 2013-9-21 18:23:36 |只看该作者 |倒序浏览
试卷: LEED AP EB模拟题 A卷[查看]
For a mechanically ventilated space, what should a project team do to achieve IEQ
Credit 1.4 IAQ Best Management Practices - Reduce Particulates in Air Distribution?
A: Use MERV 13 filters or greater for all outside air intakes and inside air recirculation returns
B: Increase the ventilation rate by 30%
C: Select air filters with lower pressure drops
D: Replace filtration media every 90 days

参考答案: A

本题解释:
Notes:
Reference: IEQ Credit 1.4, Requirements

The question is asking what is required - use MERV 13 filters

The media should be replaced according to the manufacturer\'s recommended interval,
not every 90 days.

Lower pressure drop filters will be more energy efficient, but that is not a requirement
of the credit.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-7-9 02:11 , Processed in 0.074196 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部