A project building received its first LEED certification for LEED for Existing Buildings: O&M.
When will the project need to recertify in order to maintain certification?
A: 3 years
B: 2 years
C: 4 years
D: 1 years
E: 5 years

参考答案: E

本题解释:
Notes:
See Reference Guide, Introduction, Initial Certification vs. Recertification

Buildings must recertify at least every five years whether the project received an earlie r
LEED certification or not.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-9-13 01:05 , Processed in 0.075350 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部