试卷: LEED v4 GA模拟题A卷[查看] Which of the following project areas would retrocommissioning aid? A: Operational energy efficiency B: Identifying system problems prior to occupancy C: Advanced energy metering D: Selecting environmentally preferable products 参考答案: A
本题解释: A:Retrocommissioning is ’a commissioning process that can be performed on existing buildings to identify and recognize system improvements that make the building more suitable for current use.’ - USGBC
Retrocommissioning usually occurs at least one year after the building has been occupied.
B:Commissioning (not retrocommissioning) identifies problems before occupancy.
C:This is not correct.
D:This is not correct.
|
|