试卷: LEED v4 GA模拟题A卷[查看] What is a difference between advanced energy metering and building-level energy metering? A: Advanced metering tracks building subsystems B: Advanced metering is a manual process C: Advanced metering tracks consumption at one-month intervals D: Advanced metering requires a computer simulation be completed during the design process 参考答案: A
本题解释: A:Advanced metering tracks a building subsystems - hot water systems, chillers, cooling towers, lighting, etc.
B:While it could be manual, it is more likely to be hooked into a building automation system for automatic real-time reporting.
C:Building-level energy metering also tracks consumption at one-month intervals.
D:This is not true.
|
|