试卷: LEED v4 GA模拟题C卷[查看] An owner is questioning the additional costs of submetering of a mixed-use project’s water and energy systems. For what reason should the submeters be installed? A: Submetering is a Minimum Program Requirement B: LEED requires metering by subsystem of all energy and water based systems C: The integrative process does not work without submetering data D: Identifies disparities between how a project’s water-based systems are designed to operate and how they actually perform 参考答案: D
本题解释: 正确答案:D
系统解析: B:Subsystems are not required to be metered in LEED, only building level metering is required.
In LEED v4 building level energy and water metering is a prerequisite.
In LEED v2009 sharing energy and water use with USGBC is a Minimum Program Requirement (via utility statements or metering data).
Notes:
One of the intents of water metering is to determine if a building is performing as designed.
|
|