试卷: LEED v4 ID+C模拟题A卷英文[查看] A renovation project includes removing part of an old building, re-grading some of the site, and taking down some trees for a building expansion. What item must be included in the calculations for MR Credit Construction and Demolition Waste Management Option 1 Diversion? A: Land-clearing debris from cutting down trees and shrubs B: Carpet that is not Green Label Plus certified C: Alternative daily cover (ADC) D: Asbestos ceiling tiles E: Excavated soil 参考答案: B
本题解释: Notes:Land-clearing debris is excluded from the calculations.
B:The carpet would need to be included in the calculations for the total of all construction waste management. If the carpet were recycled or donated it would be included in the percentage of construction waste diverted from landfills. |
|