试卷: LEED v4 ID+C模拟题A卷英文[查看] A hospitality project will include a common laundry room, postal area, and heated swimming pool. An independent CxA has been hired to help the project achieve EA Credit Enhanced Commissioning. What additional activities will the CxA be required for enhanced systems commissioning?(Choose 2) A: Develop an on-going commissioning plan B: Develop a systems manual for the heated swimming pool C: Review contractor submittals applicable to the heated swimming pool D: Verify that requirements for training are completed E: Implement the commissioning plan 参考答案: AC
本题解释: Notes:There are several responsibilities only the CxA can complete for Enhanced Systems Commissioning. Some items can be completed by the CxA or other members of the project team. The question specifically asks for items that the CxA is required to perform. So the correct answers can only be performed by the CxA.
Training can be done by the CxA or other project team member, that is why it is not a correct answer - the CxA is not required to do it. |
|