When designing for flexibility, project teams should focus on the portions of th

[复制链接]

1759

主题

1

好友

5712

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2016-9-30 16:29:28 |只看该作者 |倒序浏览
试卷: LEED v4 ID+C模拟题C卷英文[查看]
When designing for flexibility, project teams should focus on the portions of the project typically subject to change, which include all of the following EXCEPT:
A: HVAC services
B: Parking areas
C: Department layouts
D: Movable furniture

参考答案: B

本题解释:
Notes: The credit focuses on the space plan, services, and movable items.