试卷: LEED v4 ID+C模拟题D卷英文[查看] A project design with mechanical ventilation includes three dedicated outdoor air delivery systems with local distribution. Which filtration would be necessary for EQ Credit Enhanced IAQ Strategies?
A: MERV 13 (F7) or higher filters at each local distribution point B: MERV 13 (F7) or higher filters for each outdoor air system C: MERV 13 (F7) or higher filters at each return duct D: MERV 13 (F7) or higher filters for each outdoor exhaust 参考答案: B
本题解释: 选择B,本题解释A.This is not necessary. B.This is correct and meets the requirements.
Remember the filters must be replaced after completion of construction and before occupancy.
C.This is not correct. D.This is not required. |
|