试卷: LEED v4 ID+C模拟题D卷英文[查看] A contractor has bins on the site of a construction project for commingled waste. Which statement is true about the project\'s ability to earn MR Credit Construction and Demolition Waste Management for diverting waste? A: The project cannot earn the credit because the waste streams are not separated. B: The project can earn the credit if the waste-sorting facility sorts the materials and provides average diversion rates. C: The project can earn the credit if the waste-sorting facility sorts the materials and provides the diversion rate for the pro D: The project can earn the credit by using the average diversion rate for the waste-sorting facility if the facility is regulat 参考答案: C
本题解释: 选择C,本题解释Commingled waste can count toward the credit if the waste-sorting facility provides the diversion percentages for the project\'s specific waste. |
|