试卷: LEED v4 ID+C模拟题D卷英文[查看] A retail project fell behind schedule and the building flush out will need to occur while the space is occupied. When must the flush-out period occur if the occupants are in the space? A: After the teachers leave each day, continuing until they arrive they next day B: 24 hours prior to occupancy C: At the start of occupancy each day, continuing until the last person leaves the building each day D: 3 hours prior to occupancy and continue during occupancy 参考答案: D
本题解释: 选择D,本题解释For an occupied flush-out the flush-out must begin 3 hours prior to occupancy and continue during occupancy. Occupancy cannot begin until at least 3,500 cu. ft. outside air / sq. ft. of floor area has been introduced. |
|