试卷: LEED v4 OM模拟题A卷英文[查看] A project team is reviewing a project\'s goals. What type of analysis would be appropriate for existing building commissioning?
项目团队正在审查项目目标。什么类型的分析适合既有建筑调试? A: Documentation is outdated 过时的文档 B: The focus is on proper system operations重点是正确的系统操作 C: The building is older and hasn\'t been retrofitted recently 该建筑物较旧,最近没有改造过 D: The owner wants to make major upgrades to the building envelope 业主准备对建筑电梯进行更新 参考答案: B
本题解释: 选择B,本题解释 The Existing Building Commissioning option focuses more on controls, proper system operations and efficiency improvements.
The other choices would benefit from an ASHRAE Level 2 Energy Survey and Analysis. |
|